Schedule - As of January/April 2017

Original Contract Time - 1003 calendar days
Notice to Proceed - March 3, 2014
Estimated Completed Date - June 2017
Overall Completion - 89%

Note: Additional public meeting are planned, however no tentative dates are scheduled. Possible public meeting times may occur right before construction begins and at various times during the construction phase. Check with the city website for the most up to date information on public meeting dates and times.